Download PDF
Free Download as PDF of Business Mathematics Questions with Answers as per exam pattern, to help you in day to day learning. We provide all important questions and answers for all Exam.
25. An LPP deals with problems involving only ______
- [A] single objective.
- [B] multiple objective.
- [C] two objective.
- [D] none of these.
Answer: Option [A]
26. Which of the following is not true about feasibility?
- [A] It cannot be determined in a graphical solution of an LPP.
- [B] It is independent of the objective function.
- [C] It implies that there must be a convex region satisfying all the constraints.
- [D] Extreme points of the convex region give the optimum solution
Answer: Option [A]
27. In Graphical solution the redundant constraint is _______.
- [A] which forms the boundary of feasible region.
- [B] which do not optimizes the objective function.
- [C] which does not form boundary of feasible region.
- [D] which optimizes the objective function.
Answer: Option [C]
28. Unbounded solution in an LPP is __________.
- [A] where the objective function can be decreased indefinitely.
- [B] which maximizes the objective function.
- [C] where the objective function can be increased or decreased indefinitely.
- [D] where the objective function can be increased indefinitely.
Answer: Option [C]
29. In an LPP the solution for the problems involving more than 2 variables can be solved using
_____________.
- [A] graphical method.
- [B] simplex method.
- [C] hungarian method.
- [D] all the above
Answer: Option [B]
30. In the standard form of LPP if the objective function is of minimization then the right hand
side of the constraints should be ___________.
- [A] positive
- [B] negative.
- [C] non-negative.
- [D] zero.
Answer: Option [C]
31. The Key column in simplex method is selected when the column of Z
j-C
j is ______.
- [A] most negative.
- [B] largest negative.
- [C] positive.
- [D] zero.
Answer: Option [A]
32. In a linear programming minimization model the objective function is to be ________.
- [A] minimized.
- [B] maximized.
- [C] minimized or maximized
- [D] standardized.
Answer: Option [A]
33.Which of the following is associated with any L.P.P?
- [A] feasible solution.
- [B] optimum solution.
- [C] basic solution.
- [D] all the above.
Answer: Option [D]
34. Which of the following is not true about feasibility?
- [A] it cannot be determined in a graphical solution of an L.P.P.
- [B] it is independent of the objective function.
- [C] it implies that there must be a convex region satisfying all the constraints..
- [D] extreme points of the convex region gives the optimum solution.
Answer: Option [A]
35. The objective of network analysis is to _____.
- [A] Minimize total project duration
- [B] Minimize total project cost.
- [C] Minimize product delays,interruption and conflicts
- [D] All the above.
Answer: Option [A]
36. The slack for an activity is equal to______
- [A] LF-LS.
- [B] EF-ES.
- [C] LS-ES.
- [D] None of the above.
Answer: Option [C]
Please share this page