37. Generally the PERT technique deals with the project of ____________
- [A] Repetatative nature.
- [B] Non-repetative nature.
- [C] Determinstic nature.
- [D] None of the above.
Answer: Option [B]
38. While drawing the network diagram for each activity project we should look __________
- [A] What acitivities preceede this acitivity
- [B] What acitivities follow this acitivity.
- [C] What activity can concurrently take place with this activity.
- [D] All the above.
Answer: Option [D]
39. Float or slack analysis is useful for __________
- [A] Projects behind the schedule only.
- [B] Projects ahead of the schedule only.
- [C] Both (A) & (B)
- [D] None of the above.
Answer: Option [A]
40. Activity –on-arrow (AOA) diagram is prefeered over Activity –on-node (AON) diagram
because __________
- [A] AOA diagrams are simple to construct
- [B] AOA diagrams give a better sense of the flow of time throughout a project.
- [C] AOA diagrams do not involve dummy activites
- [D] AOA diagrams do not involve dummy activites
Answer: Option [B]
41. Crashing is the process of reducing the total time that it takes to complete a project by
expanding ___________
- [A] Additional funds.
- [B] No.of.days
- [C] Both (A) & (B)
- [D] None of the above
Answer: Option [A]
42. ___________ is the time consuming job (or) task that is a key subpart of the total project
- [A] Activity.
- [B] Event.
- [C] Node.
- [D] All the above
Answer: Option [A]
43. Network is the graphical display of a project that contains both ______ and _________
- [A] Activities and events.
- [B] Activities and dummy activities.
- [C] Both (A) & (B).
- [D] Neither (A) nor (B).
Answer: Option [A]
44. Latest finish time that an activity can be finished without _______ the entire project.
- [A] Delaying.
- [B] Planning
- [C] Both (A) & (B)
- [D] None of the above
Answer: Option [A]
45. PERT is a tool for __________ and control time
- [A] Delaying.
- [B] Planning.
- [C] Both (A) & (B)
- [D] None of the above
Answer: Option [B]
46. Project __________ phase allocates resources to work packages
- [A] Planning.
- [B] Scheduling.
- [C] Controlling.
- [D] Both (B) & (C).
Answer: Option [A]
47. A __________ is an endeavour to create a unique product service.
- [A] Project.
- [B] Network.
- [C] Activity.
- [D] Node.
Answer: Option [A]
48. In Transportation problem the preferred method of obtaining either optimal or very close to
the optimal solution is _____________.
- [A] north west corner rule.
- [B] east cost method.
- [C] vogel’s approximation method.
- [D] simplex method.
Answer: Option [C]