Identify the correct sequence with reference to environmental clearance process for new projects :

[A] Appraisal → Screening → Scoping → Public Consultation
[B] Screening → Scoping → Public Consultation → Appraisal
[C] Scoping → Public Consultation → Appraisal → Screening
[D] Public Consultation → Appraisal → Screening → Scoping
Answer & Explanation

Answer: Screening → Scoping → Public Consultation → Appraisal