61
Select the incorrect statement.
Answer: None of the above
Answer: None of the above
Answer: Activity of excavation which takes 8 units of time
Answer: Cheapest critical activity
Answer: All the above
Answer: 500 cum
Answer: Programme Evaluation and Review Technique, is event oriented
Answer: Kneading
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction isAnswer: 1, 2, 3, 4, 5
Answer: All the above
Answer: 16 days
Answer: All the above
Assertion (A): Activity 57 is critical.
Reason (R): Earliest finish time and latest finish time for events 57 are same
Select the correct answer.Answer: A is correct but R is not correct
Answer: The activity which consumes maximum time, is called a node
Answer: Its latest start time and earliest start time
Answer: All the above
Answer: None of the above
Answer: Horizontal lines
Answer: 3.5 and 25/36
Answer: All the above
Answer: Critical ratio scheduling