61
In purchasing an item or service from a supplier, which factor is not included when specifications are being developed?
[A]
Quantity requirements
[B]
Price requirements
[C]
Delivery requirement
[D]
Functional requirement
Answer: Delivery requirement
62
Buying of the annual requirements of an item during its season.
[A]
Speculative Buying
[B]
Seasonal Buying
[C]
Hand to mouth buying
[D]
Tender Buying
Answer: Speculative Buying
63
Finance must keep investment and costs low. This can be done by___________
[A]
Decreasing the number of plants and warehouses
[B]
Producing small quantities
[C]
Increasing inventory so inventory investment is at a maximum
[D]
Using short production runs
Answer: Decreasing the number of plants and warehouses
64
It is possible to increase the available capacity by:
[A]
Limiting subcontracting
[B]
Using fewer workers
[C]
Rerouting away from other work centers
[D]
Scheduling overtime
Answer: Scheduling overtime
65
In the __________________ environment, many different end items are made from a small number of components.
[A]
make-to-order
[B]
make-to-stock
[C]
assembly-to-order
[D]
engineer-to-order
66
A _________ is used when companies usually make more than one product and the same components are often used in several products.
[A]
multiple bill
[B]
single-level bill
[C]
multilevel bill
[D]
None of the above
67
__________ are purchased items received that have not entered the production process. They include purchased materials, component parts, and sub-assemblies.
[A]
Work-in-process
[B]
MRO supplies
[C]
Finished goods
[D]
Raw materials
68
___________ include hand tools, spare parts, lubricants, and cleaning supplies.
[A]
MRO supplies
[B]
Raw materials
[C]
Work-in-process
[D]
Finished goods
69
__________ inventory is held to cover random unpredictable changes in supply and demand or lead time.
[A]
Fluctuation
[B]
Anticipation
[C]
Transportation
[D]
Lot-size
70
A(n) _____________ lists all the parts needed to make one complete assembly.
[A]
indented bill
[B]
multilevel bill
[C]
single-level bill
[D]
summarized parts list
Answer: summarized parts list
71
The Gregorian calendar:
[A]
Has an equal number of days per month
[B]
Works on a decimal base
[C]
Spreads holidays evenly throughout the year
[D]
Resource planning
Answer: Presents problems for manufacturing planning and control
72
The term _____________means that the work center is overloaded and the term ________________ means the work center is under loaded.
[A]
overcapacity, under capacity
[B]
undercapacity, overcapacity
[C]
utilization, under capacity
[D]
overcapacity, utilization
Answer: overcapacity, under capacity
73
______________is concerned with the production of high-volume standard products.
[A]
Intermittent manufacturing
[B]
Product manufacturing
[C]
Flow manufacturing
[D]
All of the above
Answer: Flow manufacturing
74
An example of project manufacturing is:
[A]
Large shipbuilding
[B]
Gasoline
[C]
Automobiles
[D]
Appliances
Answer: Large shipbuilding
75
The _________________ collects all of the relevant data on a work center.
[A]
item master file
[B]
product structure file (bill of material file)
[C]
work center master file
[D]
routing file
Answer: work center master file
76
_________ is the amount of time the job is waiting at a work center before an operation begins.
[A]
Setup time
[B]
Run time
[C]
Wait time
[D]
Queue time
77
A ________________ is a legal offer to purchase.
[A]
purchase order
[B]
quotation
[C]
receiving order
[D]
supplier's invoice
78
___________specifications and standard specifications are the two major sources of specifications or ways of describing a product.
[A]
Buyer
[B]
Marketing
[C]
Production
[D]
Functional
79
Trends:
[A]
Are level
[B]
Have no change from period to period
[C]
Can rise or fall
[D]
All of the above
80
Raw Materials and WIP can be classified under-
[A]
Direct Material
[B]
Indirect Material
[C]
Finished Material
[D]
Standard Parts
Please share this page