41
The near future holds _____ uncertainty than (as) the far future.
[A]
more
[B]
the same
[C]
less
[D]
all of the above
42
______________ is usually thought of as occurring on a yearly basis, but it can also occur on a weekly or even daily basis.
[A]
Random variation
[B]
A trend
[C]
A cycle
[D]
Seasonality
43
_______________ occurs when a customer's order is received.
[A]
Order processing
[B]
Demand management
[C]
Forecasting
[D]
Random variation
44
Materials such as copper, coal, wheat, meat, and metals are:
[A]
Commodities
[B]
Standard products
[C]
Items of small value
[D]
Made-to-order items
45
_______ is most often used in wholesale or retail businesses but is also used extensively in manufacturing.
[A]
Description by function
[B]
Description by specification
[C]
Description by buyer
[D]
Description by brand
Answer: Description by brand
46
________ is the systematic use of techniques that identify a required function, establish a value for that function, and finally provide the function at the lowest overall cost.
[A]
Functional analysis
[B]
Value analysis
[C]
Functional specifications
[D]
None of the above
47
Storing inventory requires ___________________ and as inventory increases, so do these costs.
[A]
space, workers, and equipment
[B]
space and workers
[C]
workers and equipment
[D]
space and equipment
Answer: space, workers, and equipment
48
Liabilities are obligations or amounts owed by a company and include:
[A]
Long-term debt
[B]
Wages payable
[C]
Accounts payable
[D]
All of the above
49
The risks in carrying inventory are:
[A]
Obsolescence, damage, pilferage, and deterioration
[B]
Obsolescence and damage
[C]
Pilferage and deterioration
[D]
Damage and pilferage
Answer: Obsolescence, damage, pilferage, and deterioration
50
___________ is the process of multiplying the requirements by the usage quantity and recording the appropriate requirements throughout the product tree.
[A]
Exploding
[B]
Offsetting
[C]
Planning orders
[D]
Lead time
51
linked to production planning.
[A]
MRP
[B]
Capacity requirements planning
[C]
Rough-cut capacity planning
[D]
Resource planning
Answer: Resource planning
52
The inputs needed for a CRP include:
[A]
Open shop orders
[B]
Planned order released
[C]
Routings
[D]
All of the above
53
_____________ is the number of hours a work center can be used.
[A]
Available hours
[B]
Demonstrated capacity
[C]
Rated capacity
[D]
Utilization
54
Rated capacity is calculated by taking into account the work center ___________.
[A]
utilization and demonstrated capacity
[B]
efficiency and production
[C]
efficiency and demonstrated capacity
[D]
utilization and efficiency
Answer: utilization and efficiency
55
If the workload in a manufacturing plan cannot be changed, an alternative is to:
[A]
Schedule overtime
[B]
Schedule undertime
[C]
Adjust the workforce by hiring
[D]
All of the above
56
Flow of work through the shop is varied and depends on the design of a particular product. In _____________, as orders are processed, they will take more time at one workstation than at another. Thus, the work flow is not balanced.
[A]
product manufacturing
[B]
intermittent manufacturing
[C]
flow manufacturing
[D]
all of the above
Answer: intermittent manufacturing
57
Each active manufacturing order has a record in the _____________________.
[A]
shop order master file
[B]
work center master file
[C]
product structure file (bill of material file)
[D]
item master file
Answer: shop order master file
58
into two or more lots and run on two or more machines simultaneously.
[A]
Operation splitting
[B]
Operation overlapping
[C]
Infinite loading
[D]
Backward scheduling
Answer: Operation splitting
59
The objectives of purchasing include:
[A]
Ensuring the best possible service and prompt delivery by the supplier
[B]
Obtaining the goods and services at the highest price
[C]
Obtaining goods and services of the lowest quality
[D]
All of the above
Answer: Ensuring the best possible service and prompt delivery by the supplier
60
When the supplier's invoice is received, the following should agree:
[A]
The purchase order, the work order, and the production report
[B]
The material specification, the purchase requisition, and the invoice
[C]
The receiving report, the quotation, and the material specification
[D]
The purchase order, the receiving report, and the invoice
Answer: The purchase order, the receiving report, and the invoice