The expected out turn of cement concrete 1 : 2 : 4 per mason per day is

Q. The expected out turn of cement concrete 1 : 2 : 4 per mason per day is

A.            5.0 m3

B.            2.5 m3

C.            1.5 m 3

D.            None

Answer: 5.0 m3