A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.

Q. A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.

A.            26,000 m3

B.            26,500 m3

C.            27,000 m3

D.            27,500 m3

Answer: 27,500 m3

We will be happy to hear your thoughts

Leave a reply

Gkseries.com
Logo
Register New Account