The maximum number of vehicles observed in any five minute period during the peak hour is 160. If the total flow in the peak hour is 1000 vehicles

Q. The maximum number of vehicles observed in any five minute period during the peak hour is 160. If the total flow in the peak hour is 1000 vehicles, the five minute peak hour factor (round off to 2 decimal places) is _________________________

Sol:

The five-minute peak hour factor for 5 minutes is defined as the ratio of peak hourly traffic for 5 minutes to the maximum possible traffic for minutes.

Given,  (maximum number of vehicle) in 5 minutes = 160

vehicles  Flow in the peak hour = 1000 vehicles

                                          

Take Mock Tests

Government Schemes Mock Test Start Test!
Political Science Mock Test – 42 Start Test
History Test – 190 Start Test
Quantitative Aptitude Test Start Test!
Data Interpretation - Mock Test Start Test!
General Awareness - Mock Test Start Test!
Reasoning Ability - Mock Test Start Test!
We will be happy to hear your thoughts

Leave a reply

Gkseries.com
Logo
Register New Account