The activities of a project, their duration and the precedence relationships are given in the table

Q. The activities of a project, their duration and the precedence relationships are given in the table. For example, in a precedence relationship “X < Y, Z” means that X is predecessor of activities Y and Z. The time to complete the activities along the critical path is weeks.

ActivityDuration (Weeks)Precedence Relationship
A5A < B, C, D
B7B < E, F, G
C10C < I
D6D < G
E3E < H
F9F < I
G7G < I
H4H < I
I2—-

(A) 17                                                            (B) 21

(C) 23                                                             (D) 25

Ans: 23

Sol:

So critical path is A – B – F – I

Critical path duration = 23 weeks

Take Mock Tests

Government Schemes Mock Test Start Test!
Political Science Mock Test – 42 Start Test
History Test – 190 Start Test
Quantitative Aptitude Test Start Test!
Data Interpretation - Mock Test Start Test!
General Awareness - Mock Test Start Test!
Reasoning Ability - Mock Test Start Test!
We will be happy to hear your thoughts

Leave a reply

Gkseries.com
Logo
Register New Account