![In a level terrain, a vertical orebody of 20 m uniform width is worked by surface mining](https://www.gkseries.com/blog/wp-content/uploads/2023/10/In-a-level-terrain-a-vertical-orebody-of-20-m-uniform-width-is-worked-by-surface-mining.jpg)