A alone can complete a work in 18 days. A and B together can complete the work in 10(2/7) days

A alone can complete a work in 18 days. A and B together can complete the work in 10(2/7) days. A and C together can complete the work in 12 days. At what time B and C together can complete 83(1/3)%of work?

a)            18 days

b)            12 days

c)            15 days

d)            20 days

e)            24 days

Sol:

The time taken by B alone to complete the work

= (7/72) – (1/18) = (7 – 4)/72 = 1/24

= 24 days

The time taken by C alone to complete the work

=(1/12) – (1/18) = (3 – 2)/36 = 1/36

= 36 days

Work done by B and C together in 1 day = (1/24)

+ (1/36) = 5/72

So, time taken by B and C together to complete

83(1/3)%of work:

(72/5) * (250/300) = 12 days