A, B and C together can complete a work in 12 days and A and B together can complete the same work in 24 days

A, B and C together can complete a work in 12 days and A and B together can complete the same work in 24 days and the ratio of the efficiency of B and C is 2:5. A, B and C started the work and worked for 6 days. After 6 days, A and B left the work and C completed the remaining work. Find the time taken by C to complete the remaining work.

a)            24 days

b)            12 days

c)            8 days

d)            20 days

e)            15 days

Sol:

1/A + 1/B + 1/C = 1/12

1/A + 1/B = 1/24

1/C = 1/12-1/24 = 1/24

Time taken by C alone to complete the work =

24 days

Time taken by B alone to complete the work = 24

* 5/2 = 60 days

1/A + 1/60 = 1/24

1/A = 1/40

Time taken by A alone to complete the work = 40

days

LCM of 40, 60, 24 = 120

Total work = 120 units

A = 120/40 = 3 units per day

B = 120/60 = 2 units per day

C = 120/24 = 5 units per day

A, B and C work for 6 days

 Work completed by A, B and C together =

(3+2+5)*6 = 60 units

Remaining work = 120 – 60 = 60 units

Time taken by C to complete the remaining work

= 60/ 5 = 12 days

Take Mock Tests

Government Schemes Mock Test Start Test!
Political Science Mock Test – 42 Start Test
History Test – 190 Start Test
Quantitative Aptitude Test Start Test!
Data Interpretation - Mock Test Start Test!
General Awareness - Mock Test Start Test!
Reasoning Ability - Mock Test Start Test!
We will be happy to hear your thoughts

Leave a reply

Gkseries.com
Logo
Register New Account