![A contractor hires 36 men for a work, they complete 3/4th of the work in 15 days. After that work is stopped due to rain](https://www.gkseries.com/blog/wp-content/uploads/2024/03/A-contractor-hires-36-men-for-a-work-they-complete-3-4th-of-the-work-in-15-days.-After-that-work-is-stopped-due-to-rain.jpg)
A contractor hires 36 men for a work, they complete 3/4th of the work in 15 days. After that work is stopped due to rain. 25% of the completed work is destroyed by rain and 6 men falls sick. Find the time in which remaining work will be completed. ?
a) 9 days
b) 12 days
c) 8 days
d) 10 days
Sol:
Let total work = 16x
No. of days to do total work = 20 days