A and B can do a job in 12 days and B and C can do it in 16 days. A and B started working, without C. A worked for 5 days

A and B can do a job in 12 days and B and C can do it in 16 days. A and B started working, without C. A worked for 5 days and quit. B worked for 7 days and quit. C worked for a total of 13 days and finished the work. In how many days can C do the work alone?

A.      12 days

B.      24 days

C.      27 days

D.      29 days

Sol:

The number of days taken by A, B & C is as follows. 

(A + B) = 12 days  

(B + C) = 16 days

Let the total work be the LCM of the number of days taken by three of them i.e. 48 units

According to the question:  

A and B worked together for 5 days and did (4 × 5) 20 units of work.  

B and C worked together for 2 days and did (2 × 3) 6 units of work  

C finished the remaining work of (48 – 20 – 6) 22 units in days (13 – 2) 11 days.  

Hence, Efficiency of C = 22 units / 11 days = 2 units  

So, No of days taken by C to do the whole job alone = 48/ 2  

∴ 24 days

Take Mock Tests

Government Schemes Mock Test Start Test!
Political Science Mock Test – 42 Start Test
History Test – 190 Start Test
Quantitative Aptitude Test Start Test!
Data Interpretation - Mock Test Start Test!
General Awareness - Mock Test Start Test!
Reasoning Ability - Mock Test Start Test!
We will be happy to hear your thoughts

Leave a reply

Gkseries.com
Logo
Register New Account