Q. A welding operation is being performed with voltage = 30 V and current = 100 A. The cross-sectional area of the weld bead is 20 mm2. The work-piece and filler are of titanium for which the specific energy of melting is 14 J/mm3. Assuming a thermal efficiency of the welding process 70%, the welding speed (in mm/s) is (correct to two decimal places).

Ans: 7.49 – 7.51

Sol: