Home » About 50 units are required every day for a machine. A fixed cost of ₹ 50 is incurred for placing an order. The inventory carrying cost per unit amounts to ₹ 0.02 per day. The lead period is 32 days. Economic Order Quantity is
About 50 units are required every day for a machine. A fixed cost of ₹ 50 is incurred for placing an order. The inventory carrying cost per unit amounts to ₹ 0.02 per day. The lead period is 32 days. Economic Order Quantity is
April 27, 2022
69 Views
Q. About 50 units are required every day for a machine. A fixed cost of ₹ 50 is incurred for placing an order. The inventory carrying cost per unit amounts to ₹ 0.02 per day. The lead period is 32 days. Economic Order Quantity is