Detailed drawing is not necessarily required for which of the following estimate?

Q. Detailed drawing is not necessarily required for which of the following estimate?

A.            Detailed estimate

B.            Revised estimate

C.            Supplementary estimate

D.            Rough cost estimate

Answer: Detailed estimate