Home » If 3 men can do a work in 2 days and 4 boys can do the same work in 6 days, then in how many days will the same work be completed by 8 men and 8 boys? Quantitative aptitude If 3 men can do a work in 2 days and 4 boys can do the same work in 6 days, then in how many days will the same work be completed by 8 men and 8 boys? July 26, 2023 469 Views QuestionIf 3 men can do a work in 2 days and 4 boys can do the same work in 6 days, then in how many days will the same work be completed by 8 men and 8 boys?Typemultiple_choiceOption2 daysincorrectOption3/5 DayscorrectOption1.5 DaysincorrectOption3/4 Daysincorrect Solution
A vessel of 115 litres is filled with milk and water. 70% of milk and 40% of water is taken out of the vessel it is found that the vessel is
A manufacture of patent medicines gives 2 dozen extra bottles of the medicine for every order of 15 dozens a discount of 25%