Home » If 3 men can do a work in 2 days and 4 boys can do the same work in 6 days, then in how many days will the same work be completed by 8 men and 8 boys? Quantitative aptitude If 3 men can do a work in 2 days and 4 boys can do the same work in 6 days, then in how many days will the same work be completed by 8 men and 8 boys? July 26, 2023 466 Views QuestionIf 3 men can do a work in 2 days and 4 boys can do the same work in 6 days, then in how many days will the same work be completed by 8 men and 8 boys?Typemultiple_choiceOption2 daysincorrectOption3/5 DayscorrectOption1.5 DaysincorrectOption3/4 Daysincorrect Solution