In a company, the weekly minimum and maximum consumption of Material-A is 25 and 75 units respectively. The re-order quantity as fixed by the company is 300 units. The material is received within 4 to 6 weeks from the issue of supply order. The maximum level of Material-A is

In a company, the weekly minimum and maximum consumption of Material-A is 25

Q. In a company, the weekly minimum and maximum consumption of Material-A is 25 and 75 units respectively. The re-order quantity as fixed by the company is 300 units. The material is received within 4 to 6 weeks from the issue of supply order. The maximum level of Material-A is

A.            640 Units

B.            650 Units

C.            175 Units

D.            560 Units

Answer: 650 Units