NTPC has developed an infrastructure at Rihand project in Uttar Pradesh to transport fly ash in bulk to cement plants, located at distance, at a cheaper cost. The development is in line with NTPC’s commitment towards 100 percent utilization of fly ash from power plants.
Daily Current Affairs Quiz 2020
Key-Points
The effort marks the beginning of a new era for the transportation of fly ash from a remote location to a consumption centre, enabling power plants for upgrading the utilization of fly ash.
The development is in line with NTPC’s commitment towards 100 percent utilization of fly ash from power plants. During the financial year 2019-20, almost 44.33 million tonnes of fly ash was utilized for various productive purposes.
Rihand Super Thermal Power Project is located in Sonbhadra district of Uttar Pradesh. The power plant is one of the coal based power plants of NTPC Limited.
The coal for the plant is derived from Amlori and Dudhichua mines. The water source is from Rihand Reservoir which is constructed on Son river.