![In Critical Path Method (CPM) for time scheduling, ‘forward pass calculation’ is carried out for determining](https://www.gkseries.com/blog/wp-content/uploads/thumbs_dir/In-Critical-Path-Method-CPM-for-time-scheduling-‘forward-pass-calculation-is-carried-out-for-determining-qcc6dw7klurad09dhtft6xibj0k0zdmvpi7p85x0v4.jpg)
Q. In Critical Path Method (CPM) for time scheduling, ‘forward pass calculation’ is carried out for determining (A) Late start and early finish time (B) Early start and early finish time (C) Late start and late finish time (D) Early start and late finish time ...