The Union Cabinet has given its approval for Provision of Submarine Optical Fibre Cable Connectivity between Mainland (Kochi) and Lakshadweep Islands (KLI Project).
Daily Current Affairs Quiz 2020
Key-Points
The Project envisages provision of a direct communication link through a dedicated submarine Optical Fibre Cable (OFC) between Kochi and 11 Islands of Lakshadweep viz. Kavaratti, Kalpeni, Agati, Amini, Androth, Minicoy, Bangaram, Bitra, Chetlat, Kiltan & Kadmat.
Financial implications: The estimated cost of implementation is about Rs. 1072 crore including operational expenses for 5 years. The Project would be funded by Universal Service Obligation Fund.
Impact: The project will vastly improve telecommunication facility in the Lakshadweep Islands by providing large bandwidth.
Target: The project is targeted to be completed by May 2023.
Implementation Strategy:
- Bharat Sanchar Nigam Ltd. (BSNL) has been nominated as Project Execution Agency and Telecommunications Consultant India Ltd. (TCIL) as the Technical Consultant of the Project to assist Universal Service Obligation Fund, Department of Telecommunications.
- The ownership of the asset under the project will rest with USOF, the funding agency, under DoT.