Home ยป The estimated time required to complete an activity is known as Estimation and Costing MCQs The estimated time required to complete an activity is known as April 23, 2022 1 View Q. The estimated time required to complete an activity is known as A. Duration B. Restraint C. Constraint D. Float Answer: Float