Home » The estimated time required to complete an activity is known as Estimation and Costing MCQs The estimated time required to complete an activity is known as April 23, 2022 1 View Q. The estimated time required to complete an activity is known as A. Duration B. Restraint C. Constraint D. Float Answer: Float