The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is
Q. The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is
A. 1.00 m3
B. 1.25 m3
C. 1.50 m3
D. 1.75 m3
Answer: 1.25 m3