Q. The expected out turn of cement concrete 1 : 2 : 4 per mason per day is
A. 5.0 m3
B. 2.5 m3
C. 1.5 m 3
D. None
Answer: 5.0 m3
A. 5.0 m3
B. 2.5 m3
C. 1.5 m 3
D. None
Answer: 5.0 m3