![The expected out turn of half brick partition wall per mason per day is](https://www.gkseries.com/blog/wp-content/uploads/2022/04/The-expected-out-turn-of-half-brick-partition-wall-per-mason-per-day-is.png)
Q. The expected out turn of half brick partition wall per mason per day is
A. 1.5 m 3
B. 2.0 m3
C. 4.0 m2
D. 5.0 m2
Answer: 2.0 m3
A. 1.5 m 3
B. 2.0 m3
C. 4.0 m2
D. 5.0 m2
Answer: 2.0 m3
Government Schemes Mock Test | Start Test! |
Political Science Mock Test – 42 | Start Test |
History Test – 190 | Start Test |
Quantitative Aptitude Test | Start Test! | Data Interpretation - Mock Test | Start Test! |
General Awareness - Mock Test | Start Test! |
Reasoning Ability - Mock Test | Start Test! |