The maximum and minimum lead time is 4 weeks and 3 weeks respectively. If the maximum and minimum weekly consumption is 25 units and 20 units respectively, the re-ordering level will be

The maximum and minimum lead time is 4 weeks and 3 weeks respectively. If the maximum and minimum weekly consumption is 25 units and 20 units respectively, the re-ordering level will be

Q. The maximum and minimum lead time is 4 weeks and 3 weeks respectively. If the maximum and minimum weekly consumption is 25 units and 20 units respectively, the re-ordering level will be

A.            100 Units

B.            110 Units

C.            120 Units

D.            140 Units

Answer: 100 Units