Q. The rate of payment is made for 100 cu m (per % cu m) in case of
A. Excavation in trenches for foundation
B. Earth work in excavation
C. Rock cutting
D. All the above
Answer: All the above
A. Excavation in trenches for foundation
B. Earth work in excavation
C. Rock cutting
D. All the above
Answer: All the above