Q. Which of the following formula cannot be used to calculate re-order level?
A. Minimum level + consumption during lead time
B. Maximum consumption × maximum re-order period
C. Maximum consumption × lead time + safety stock
D. Minimum consumption × minimum re-order period
Answer: Minimum consumption × minimum re-order period