With reference to the Electricity (Transmission system Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021, consider the following statements:
1. It empowers state power distribution and transmission companies to determine their transmission requirements and build them.
2. The Central Electricity Authority shall prepare a short-term plan every year on rolling basis for next 5 years and perspective plan every alternative year on rolling basis for next 10 years.
Which of the statements given above is/are correct?
A. 1 Only
B. 2 Only
C. Both 1 & 2
D. None
Answer: Both 1 & 2
Explanation:
The Union Ministry of Power has promulgated the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules, 2021.
The rules under pir a system of transmission access which is termed as a General Network Access in the inter-state transmission system.
This provides flexibility to the state as well as the generating stations to acquire, hold and transfer transmission capacity as per their requirement.