Answer: 9 days
Answer: 9 days
Article and Schedule Quiz | Start Test! |
Answer: All the above
Answer: Applying the theory' of probability to sample testing or inspection
Answer: Variation in cost in materials element, labour element and petrol-oil-lubricant element
Answer: Independent float
Answer: Dipper shovel
Answer: Loose sand
Answer: Identify the activities, which can be delayed without affecting the total float of succeeding activity
Answer: Beta distribution curve
Answer: Less than X
Answer: Moist loam
Answer: The soil survey, traffic survey, concept design and approximate cost
Answer: On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope