Construction Planning and Management Quiz | Construction Planning and Management Multiple Choice Questions and Answers

Sports GK Questions and Answers 2024 (Latest Updated)

Awards & Honours GK Questions 2024 (Latest Updated)

Questions
1 For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
A 8 days
B 9 days
C 10 days
D 15 days

Answer: 9 days
2 A critical ratio scheduling
A Determines the status of each activity
B Adjusts automatically changes in activity progress
C Is a dynamic system
D None of these

Answer: None of these
Advertisement
Article and Schedule Quiz Start Test!
DOWNLOAD CURRENT AFFAIRS PDF FROM APP
3 For the network shown in the given figure, the expected time for the activity
A 1-2 is 4
B 2-3 is 7
C 3-4 is 8
D All the above

Answer: All the above
4 At a work site, statistical quality control of concrete means
A Measurement of risks to eliminate failures
B Applying the theory' of probability to sample testing or inspection
C Reduction in wastage of inspection costs
D Reduction in costs for the removal of defects

Answer: Applying the theory' of probability to sample testing or inspection
5 Critical path method
A Is an improvement upon bar chart method
B Provides a realistic approach to daily problems
C Avoids delays which are very common in bar charts
D All the above

Answer: All the above
6 During the construction period, price variation clause in contracts caters to
A Increase in rates of only important materials
B Variation in cost in materials element, labour element and petrol-oil-lubricant element
C Variation in total cost of the project on an ad hoc basis
D Rate of inflation

Answer: Variation in cost in materials element, labour element and petrol-oil-lubricant element
7 The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
A Total float
B Free float
C Interfering float
D Independent float

Answer: Independent float
8 Updating may result in
A Change of critical path
B Decrease of project completion time
C Increase of project completion time
D All of the above

Answer: All of the above
9 Which of the following earth moving machines has the shortest cycle time?
A Drag line
B Hoe
C Clam shell
D Dipper shovel

Answer: Dipper shovel
10 Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
A Concrete
B Loose sand
C Asphalt
D Firm earth

Answer: Loose sand
11 Grader is used mainly for
A Trimming and finishing
B Shaping and trimming
C Finishing and shaping
D Finishing, shaping and trimming

Answer: Finishing, shaping and trimming
12 Free float is mainly used to
A Identify the activities which can be delayed without affecting the total float of preceding activity
B Identify the activities, which can be delayed without affecting the total float of succeeding activity
C Establish priorities
D Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities

Answer: Identify the activities, which can be delayed without affecting the total float of succeeding activity
13 In PERT analysis, the time estimates of activities and probability of their occurrence follow
A Normal distribution curve
B Poisson's distribution curve
C Beta distribution curve
D None of the above

Answer: Beta distribution curve
14 If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be
A Equal to X
B More than X
C Less than X
D Any of the above

Answer: Less than X
15 For which of the following materials, the output of power shovels for a fixed shovel size will be maximum
A Moist loam
B Good common earth
C Well blasted rock
D Wet sticky clay

Answer: Moist loam
16 Preliminary project report for a road project must contain
A The detailed estimated cost based on detailed design
B The several alternatives of the project that have been considered
C The soil survey, traffic survey, concept design and approximate cost
D The contract documents for inviting tenders

Answer: The soil survey, traffic survey, concept design and approximate cost
17 Sensitivity analysis is a study of
A Comparison of profit and loss
B Comparison of assets and liabilities
C Change in output due to change in input
D Economics of cost and benefits of the project

Answer: Change in output due to change in input
18 In resources levelling
A Total duration of project is reduced
B Total duration of project is increased
C Uniform demand of resources is achieved
D Cost of project is controlled

Answer: Uniform demand of resources is achieved
19 Which of the following does not represent an activity?
A Site located
B Foundation is being dug
C The office area is being cleaned
D The invitations are being sent

Answer: Site located
20 In time-cost optimization of a project, crashing is done.
A On all the activities
B On all the activities lying on the critical path
C Only on activities lying on the original critical path and having flatter cost slopes
D On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

Answer: On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

Random GK Questions

Assam Direct Recruitment Test Series

Teacher Eligibility Test

Assam Direct Recruitment Test Series