25. _____________is used to reduce the game.
- [A] Transportation Problem
- [B] Assignment Problem
- [C] Dual simplex method
- [D] Graphical Method
Answer: Option [D]
26. _____is a mathematical technique used to solve the problem of allocating limited resource among the competing
activities
- [A] Linear Programming problem
- [B] Assignment Problem
- [C] Replacement Problem
- [D] Non linear Programming Problem
Answer: Option [A]
27. Traveling salesman problem will have a total of _____different sequences.
- [A] n!
- [B] n-1
- [C] (n-a)!.
- [D] n
Answer: Option [D]
28. If there exists a saddle point for a given problem it, implies that the players are using ______strategies.
- [A] Pure
- [B] Mixed
- [C] Optimal
- [D] Pure and Mixed
Answer: Option [A]
29. FCFS refers to _______in queueing theory.
- [A] First Come First Serve
- [B] Last In First Out
- [C] Service In Random Order
- [D] Fastest Server Rule
Answer: Option [A]
30. SIRO refers to _______in queueing theory.
- [A] First In First Out
- [B] Last In First Out
- [C] Service In Random Order
- [D] Fastest Server Rule
Answer: Option [C]
31. If a customers decides not to enter the queue since it is too long is called_________.
- [A] balking
- [B] reneging
- [C] jockeying
- [D] queue
Answer: Option [A]
32. When there are two or more parallel queues and customer move from one queue to another queue it is
called___________
- [A] balking
- [B] reneging
- [C] jockeying
- [D] system capacity
Answer: Option [C]
33. If the operating characteristic vary within time is called_____.
- [A] balking
- [B] reneging
- [C] transient state
- [D] steady state
Answer: Option [C]
34. The __________ time for an activity can be reduced by using increased resources.
- [A] normal
- [B] optimistic
- [C] pessimistic
- [D] most likely
Answer: Option [A]
35. Graphical method of linear programming is useful when the number of decision variable are _______
Answer: Option [A]
36. The activity cost corresponding to the crash time is called the _____.
- [A] critical time
- [B] normal time
- [C] cost slope
- [D] crash cost
Answer: Option [D]