GkSeries.com

Short Interview Questions and Answers on Software Engineering

(6) Risk analysis of a project is done in :
[A] System Analysis phase
[B] Feasibility Study
[C] Implementation phase
[D] Maintenance phase

Comment

Answer: Option [B]
(7) In which step of SDLC project termination could be done ?
[A] Design phase
[B] System Maintenance phase
[C] Feasibility Study phase
[D] Coding phase

Comment

Answer: Option [C]

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

(8) The fundamental objective of system analysis is to :
[A] understand computer hardware
[B] train managers in mathematical analysis
[C] study and understand a complex system and modify it in some way
[D] run simulation programmes

Comment

Answer: Option [C]
(9) Which one of the following is not stage of SDLC ?
[A] System analysis
[B] Problem identification
[C] System Design
[D] Feasibility study

Comment

Answer: Option [B]
(10) An iterative process of system development in which requirements are converted to a working system that is continually revised through close work between an analyst and user is called
[A] Waterfall modeling
[B] Iterative modeling
[C] Spiral modeling
[D] None of these above

Comment

Answer: Option [C]

Please share this page

Chapters

Click Here to Read more questions

Teacher Eligibility Test