(1)
The probability of completing the project can be estimated based upon the ____ .
Answer: Normal distribution curve.
Answer: Normal distribution curve.
Answer: Low
Answer: Work Breakdown Structure (WBS).
Answer: Analogy
Answer: Bottom-up
Answer: All of the above
Answer: Time, Responsiveness, Information sharing, Processes, structured planning
Answer: Planning process
Answer: All of the above
Answer: Both (A) and (B)