Business Mathematics - Questions and Answers for Competitive Exams | GkSeries

Sports GK Questions and Answers 2024 (Latest Updated)

Awards & Honours GK Questions 2024 (Latest Updated)

Questions
37. Generally the PERT technique deals with the project of ____________
  • [A] Repetatative nature.
  • [B] Non-repetative nature.
  • [C] Determinstic nature.
  • [D] None of the above.

Answer: Option [B]

38. While drawing the network diagram for each activity project we should look __________
  • [A] What acitivities preceede this acitivity
  • [B] What acitivities follow this acitivity.
  • [C] What activity can concurrently take place with this activity.
  • [D] All the above.

Answer: Option [D]

Advertisement
Article and Schedule Quiz Start Test!
DOWNLOAD CURRENT AFFAIRS PDF FROM APP
39. Float or slack analysis is useful for __________
  • [A] Projects behind the schedule only.
  • [B] Projects ahead of the schedule only.
  • [C] Both (A) & (B)
  • [D] None of the above.

Answer: Option [A]

40. Activity –on-arrow (AOA) diagram is prefeered over Activity –on-node (AON) diagram because __________
  • [A] AOA diagrams are simple to construct
  • [B] AOA diagrams give a better sense of the flow of time throughout a project.
  • [C] AOA diagrams do not involve dummy activites
  • [D] AOA diagrams do not involve dummy activites

Answer: Option [B]

41. Crashing is the process of reducing the total time that it takes to complete a project by expanding ___________
  • [A] Additional funds.
  • [B] No.of.days
  • [C] Both (A) & (B)
  • [D] None of the above

Answer: Option [A]

42. ___________ is the time consuming job (or) task that is a key subpart of the total project
  • [A] Activity.
  • [B] Event.
  • [C] Node.
  • [D] All the above

Answer: Option [A]

43. Network is the graphical display of a project that contains both ______ and _________
  • [A] Activities and events.
  • [B] Activities and dummy activities.
  • [C] Both (A) & (B).
  • [D] Neither (A) nor (B).

Answer: Option [A]

44. Latest finish time that an activity can be finished without _______ the entire project.
  • [A] Delaying.
  • [B] Planning
  • [C] Both (A) & (B)
  • [D] None of the above

Answer: Option [A]

45. PERT is a tool for __________ and control time
  • [A] Delaying.
  • [B] Planning.
  • [C] Both (A) & (B)
  • [D] None of the above

Answer: Option [B]

46. Project __________ phase allocates resources to work packages
  • [A] Planning.
  • [B] Scheduling.
  • [C] Controlling.
  • [D] Both (B) & (C).

Answer: Option [A]

47. A __________ is an endeavour to create a unique product service.
  • [A] Project.
  • [B] Network.
  • [C] Activity.
  • [D] Node.

Answer: Option [A]

48. In Transportation problem the preferred method of obtaining either optimal or very close to the optimal solution is _____________.
  • [A] north west corner rule.
  • [B] east cost method.
  • [C] vogel’s approximation method.
  • [D] simplex method.

Answer: Option [C]

Random GK Questions

Assam Direct Recruitment Test Series

Teacher Eligibility Test

Assam Direct Recruitment Test Series