61
Pick up the correct statement from the following:
[A]
The bending of bars near supports is generally at 45°
[B]
The bent up bars at a support resist the sharing force
[C]
The bent up bars at a support resist the negative bending moment
[D]
All the above
62
The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is
[A]
(6 + 12) chains
[B]
(6 + 18) chains
[C]
(6 + 15) chains
[D]
None of these
63
Pick up the correct statement from the following:
[A]
All pipes are measured along the centre line of the pipes in metres
[B]
All pipes and fittings are classified according to their diameters
[C]
The diameter of the pipes is the nominal diameter of internal bore
[D]
All the above
64
Pick up the correct statement in case of water supply.
[A]
Pipes are classified according to their sizes and quality
[B]
Cutting through walls and floors are included with the item
[C]
Pipes laid in trenches and pipes fixed to walls are measured separately
[D]
All the above
65
The total length of a cranked bar through a distance D. at 45° in case of a beam of effective length L, is
[A]
L + (2 × 0.42 d)
[B]
L – (0.42 d)
[C]
L – (2 × 0.4 d)
[D]
L + 0.42 d
66
If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is
[A]
Bd + Sd2
[B]
½ (Bd + Sd2)
[C]
B × d – Sd1/2
[D]
B + d + Sd
67
The minimum width of a septic tank is taken
[A]
75 cm
[B]
90 cm
[C]
70 cm
[D]
80 cm
68
For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is
[A]
0.274 m3
[B]
0.247 m3
[C]
0.200 m3
[D]
None of the above