(21) For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
[A] 0.94 m3
[B] 1.00 m3
[C] 0.98 m3
[D] 0.90 m3
Answer: 0.94 m3
(22) Size, capacity and materials need be specified for
[A] Ball valves
[B] Bib-cocks
[C] Stop-cocks
[D] All the above
Answer: All the above

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

(23) Berms are provided in canals if these are
[A] Partly in excavation and partly in embankment
[B] Fully in embankment
[C] Fully in excavation
[D] All the above
Answer: Partly in excavation and partly in embankment
(24) The rate of payment is made for 100 cu m (per % cu m) in case of
[A] Excavation in trenches for foundation
[B] Earth work in excavation
[C] Rock cutting
[D] All the above
Answer: All the above
(25) The main factor to be considered while preparing a detailed estimate, is
[A] Quantity of the materials
[B] Availability of materials
[C] Transportation of materials
[D] All the above
Answer: All the above
(26) If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by
[A] Prismoidal formula
[B] Mid-section formula
[C] Trapezoidal formula
[D] All the above
Answer: All the above
(27) While estimating the qualities for the construction of a building, the correct metric unit is
[A] Litre for capacity
[B] Square metres for volume
[C] Cubic metre for area
[D] None of these
Answer: Litre for capacity
(28) In the mid-section formula
[A] The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections
[B] The area of mid-sections is calculated by using mean depth
[C] The mean depth is the average of depths of two consecutive sections
[D] All of the above
Answer: All of the above
(29) Referring of given figure, pick up the correct statement from the following:
[A] Length of short walls in-to-in is 3.20 m
[B] The total length of centre line of four walls is 20 m
[C] Length of long wall out-to -out is 6.80 m
[D] All the above
Answer: All the above
(30) According to Indian Standards Institute, the actual size of modular bricks is
[A] 19 cm × 9 cm × 9 cm
[B] 20 cm × 10 cm × 10 cm
[C] 25 cm × 13 cm × 7.5 cm
[D] 23 cm × 11.5 cm × 7.5 cm
Answer: 19 cm × 9 cm × 9 cm
31 The following item of earth work is not measured separately.
[A] Steps in deep excavation
[B] Site clearance
[C] Setting out of works
[D] All the above
Answer: All the above
32 The measurement is made in square metre in case of
[A] Hollow concrete block wall
[B] R.C.C. structure
[C] Cement concrete in foundation
[D] None of these
Answer: None of these
33 Cost of fittings and their fixing is specified for the following sanitary fittings
[A] Lavatory basins
[B] Flushing pipes
[C] Water closets
[D] All the above
Answer: All the above
34 Pick up the correct statement from the following:
[A] Glazing is measured in sq.m
[B] Plastering is measured in sq.m
[C] Pointing is measured in sq.m
[D] All the above
Answer: All the above
35 The value of ‘B’ of Indian type W.C. shown in the given figure is:
[A] 30 cm
[B] 50 cm
[C] 45 cm
[D] None
Answer: 45 cm
36 Pick up the excavation where measurements are made in square metres for payment.
[A] Ordinary cuttings up to 1 m
[B] Surface dressing up to 15 cm depths
[C] Surface excavation up to 30 cm depths
[D] Both B. and C.
Answer: Both B. and C.
37 In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and
[A] Half breadth of wall on each side
[B] One fourth breadth of wall on each side
[C] Breadth of the wall
[D] None of these
Answer: Half breadth of wall on each side
38 The measurement is not made in square metres in case of
[A] R.C. Chhajja
[B] D.P.C. (Damp proof course)
[C] Concrete Jeffries
[D] Form works
Answer: R.C. Chhajja
39 The trap which is provided to disconnect the house drain from the street sewer is called
[A] Interception manhole
[B] Intercepting trap
[C] Master trap
[D] All the above
Answer: All the above
40 While preparing a detailed estimate
[A] Volume should be measured correct to 0.01 cum
[B] Area should be measured correct to 0.01 sqm
[C] Dimension should be measured correct to 0.01 m
[D] All the above
Answer: All the above