Questions
21 For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
A 0.94 m3
B 1.00 m3
C 0.98 m3
D 0.90 m3

Answer: 0.94 m3
22 Size, capacity and materials need be specified for
A Ball valves
B Bib-cocks
C Stop-cocks
D All the above

Answer: All the above
Advertisement
Article and Schedule Quiz Start Test!
DOWNLOAD CURRENT AFFAIRS PDF FROM APP
23 Berms are provided in canals if these are
A Partly in excavation and partly in embankment
B Fully in embankment
C Fully in excavation
D All the above

Answer: Partly in excavation and partly in embankment
24 The rate of payment is made for 100 cu m (per % cu m) in case of
A Excavation in trenches for foundation
B Earth work in excavation
C Rock cutting
D All the above

Answer: All the above
25 The main factor to be considered while preparing a detailed estimate, is
A Quantity of the materials
B Availability of materials
C Transportation of materials
D All the above

Answer: All the above
26 If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by
A Prismoidal formula
B Mid-section formula
C Trapezoidal formula
D All the above

Answer: All the above
27 While estimating the qualities for the construction of a building, the correct metric unit is
A Litre for capacity
B Square metres for volume
C Cubic metre for area
D None of these

Answer: Litre for capacity
28 In the mid-section formula
A The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections
B The area of mid-sections is calculated by using mean depth
C The mean depth is the average of depths of two consecutive sections
D All of the above

Answer: All of the above
29 Referring of given figure, pick up the correct statement from the following:
A Length of short walls in-to-in is 3.20 m
B The total length of centre line of four walls is 20 m
C Length of long wall out-to -out is 6.80 m
D All the above

Answer: All the above
30 According to Indian Standards Institute, the actual size of modular bricks is
A 19 cm × 9 cm × 9 cm
B 20 cm × 10 cm × 10 cm
C 25 cm × 13 cm × 7.5 cm
D 23 cm × 11.5 cm × 7.5 cm

Answer: 19 cm × 9 cm × 9 cm
31 The following item of earth work is not measured separately.
A Steps in deep excavation
B Site clearance
C Setting out of works
D All the above

Answer: All the above
32 The measurement is made in square metre in case of
A Hollow concrete block wall
B R.C.C. structure
C Cement concrete in foundation
D None of these

Answer: None of these
33 Cost of fittings and their fixing is specified for the following sanitary fittings
A Lavatory basins
B Flushing pipes
C Water closets
D All the above

Answer: All the above
34 Pick up the correct statement from the following:
A Glazing is measured in sq.m
B Plastering is measured in sq.m
C Pointing is measured in sq.m
D All the above

Answer: All the above
35 The value of ‘B’ of Indian type W.C. shown in the given figure is:
A 30 cm
B 50 cm
C 45 cm
D None

Answer: 45 cm
36 Pick up the excavation where measurements are made in square metres for payment.
A Ordinary cuttings up to 1 m
B Surface dressing up to 15 cm depths
C Surface excavation up to 30 cm depths
D Both B. and C.

Answer: Both B. and C.
37 In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and
A Half breadth of wall on each side
B One fourth breadth of wall on each side
C Breadth of the wall
D None of these

Answer: Half breadth of wall on each side
38 The measurement is not made in square metres in case of
A R.C. Chhajja
B D.P.C. (Damp proof course)
C Concrete Jeffries
D Form works

Answer: R.C. Chhajja
39 The trap which is provided to disconnect the house drain from the street sewer is called
A Interception manhole
B Intercepting trap
C Master trap
D All the above

Answer: All the above
40 While preparing a detailed estimate
A Volume should be measured correct to 0.01 cum
B Area should be measured correct to 0.01 sqm
C Dimension should be measured correct to 0.01 m
D All the above

Answer: All the above